RENCANA ANGGARAN BIAYA
PROYEK  : RENOVASI MASJID 
PEKERJAAN  : RENOVASI BANGUNAN 1 LANTAI
LOKASI : YOGYAKARTA
TAHUN ANGGARAN : 2014
NO URAIAN PEKERJAAN VOLUME SAT. HARGA SATUAN   JUMLAH HARGA  
    (RP.)   (RP.)  
1 2 3 4 5
  PEKERJAAN BANGUNAN BAGIAN DEPAN BESERTA PAGARNYA        
I PEKERJAAN PAGAR          
1 Dinding pagar                   3,08 M3       1.545.000,00                    4.758.600,00  
2 Ornamen tiang pagar                   3,00 unit       2.500.000,00                    7.500.000,00  
3 Gapura main entrance                   2,00 unit       9.500.000,00                  19.000.000,00  
4 Ornamen horisontal yg menghubungkan antar gapura                  1,00 unit       9.550.000,00                    9.550.000,00  
                       40.808.600,00  
II PEKERJAAN ATAP KANOPI PENUTUP TERAS        
1 Rangka atap kanopi baja ringan, hollow & kolom penyangga              102,00 M2          250.000,00                  25.500.000,00  
2 Penutup atap kanopi polikarbonat                  99,00 M2          215.000,00                  21.285.000,00  
                       46.785.000,00  
III PEKERJAAN TOWER 18 METER          
1 Pekerjaan beton (borpeil, tiang, & puncak)                 51,00 M3       2.350.000,00                119.850.000,00  
2 Pekerjaan finishing permukaan                210,00 M2          117.000,00                  24.570.000,00  
3 Pekerjaan ornamen tengah tiang                 32,00 M2           31.373,00                    1.003.936,00  
4 Pekerjaan ornamen puncak tiang                   1,00 unit       4.550.000,00                    4.550.000,00  
5 Pekerjaan instalasi kabel & speaker                   1,00 ls       7.500.000,00                    7.500.000,00  
           
                       157.708.496,00  
    SUB TOTAL HARGA FISIK                           245.302.096,00  
    PPN 10 %                              24.530.209,60  
    SUB TOTAL HARGA FISIK + PPN 10%                        269.832.305,60  
    DIBULATKAN                            269.832.000,00  
         
                       
  BIAYA DESIGN, SUPERVISI, & IMB    
  PERENCANAAN TEKNIS (Kepmen Kimpraswil No. 332/KPTS/M/2002=6.83 % X SUB TOTAL PER UNIT                18.429.525,60  
  PENGAWASAN TEKNIS (Kepmen Kimpraswil No. 332/KPTS/M/2002 =  4.63 % X SUB TOTAL PER UNIT                12.493.221,60  
  IMB= 1 % X SUB TOTAL HARGA                  2.698.320,00  
                                   33.621.067,20  
  J U M L A H              303.453.067,20  
    DIBULATKAN                            303.450.000,00  