RENCANA ANGGARAN BIAYA | |||||||||||
PROYEK | : | RENOVASI MASJID | |||||||||
PEKERJAAN | : | RENOVASI BANGUNAN 1 LANTAI | |||||||||
LOKASI | : | YOGYAKARTA | |||||||||
TAHUN ANGGARAN | : | 2014 | |||||||||
NO | URAIAN PEKERJAAN | VOLUME | SAT. | HARGA SATUAN | JUMLAH HARGA | ||||||
(RP.) | (RP.) | ||||||||||
1 | 2 | 3 | 4 | 5 | |||||||
PEKERJAAN BANGUNAN BAGIAN DEPAN BESERTA PAGARNYA | |||||||||||
I | PEKERJAAN PAGAR | ||||||||||
1 | Dinding pagar | 3,08 | M3 | 1.545.000,00 | 4.758.600,00 | ||||||
2 | Ornamen tiang pagar | 3,00 | unit | 2.500.000,00 | 7.500.000,00 | ||||||
3 | Gapura main entrance | 2,00 | unit | 9.500.000,00 | 19.000.000,00 | ||||||
4 | Ornamen horisontal yg menghubungkan antar gapura | 1,00 | unit | 9.550.000,00 | 9.550.000,00 | ||||||
40.808.600,00 | |||||||||||
II | PEKERJAAN ATAP KANOPI PENUTUP TERAS | ||||||||||
1 | Rangka atap kanopi baja ringan, hollow & kolom penyangga | 102,00 | M2 | 250.000,00 | 25.500.000,00 | ||||||
2 | Penutup atap kanopi polikarbonat | 99,00 | M2 | 215.000,00 | 21.285.000,00 | ||||||
46.785.000,00 | |||||||||||
III | PEKERJAAN TOWER 18 METER | ||||||||||
1 | Pekerjaan beton (borpeil, tiang, & puncak) | 51,00 | M3 | 2.350.000,00 | 119.850.000,00 | ||||||
2 | Pekerjaan finishing permukaan | 210,00 | M2 | 117.000,00 | 24.570.000,00 | ||||||
3 | Pekerjaan ornamen tengah tiang | 32,00 | M2 | 31.373,00 | 1.003.936,00 | ||||||
4 | Pekerjaan ornamen puncak tiang | 1,00 | unit | 4.550.000,00 | 4.550.000,00 | ||||||
5 | Pekerjaan instalasi kabel & speaker | 1,00 | ls | 7.500.000,00 | 7.500.000,00 | ||||||
157.708.496,00 | |||||||||||
SUB TOTAL HARGA FISIK | 245.302.096,00 | ||||||||||
PPN 10 % | 24.530.209,60 | ||||||||||
SUB TOTAL HARGA FISIK + PPN 10% | 269.832.305,60 | ||||||||||
DIBULATKAN | 269.832.000,00 | ||||||||||
BIAYA DESIGN, SUPERVISI, & IMB | |||||||||||
PERENCANAAN TEKNIS (Kepmen Kimpraswil No. 332/KPTS/M/2002=6.83 % X SUB TOTAL PER UNIT | 18.429.525,60 | ||||||||||
PENGAWASAN TEKNIS (Kepmen Kimpraswil No. 332/KPTS/M/2002 = 4.63 % X SUB TOTAL PER UNIT | 12.493.221,60 | ||||||||||
IMB= 1 % X SUB TOTAL HARGA | 2.698.320,00 | ||||||||||
33.621.067,20 | |||||||||||
J U M L A H | 303.453.067,20 | ||||||||||
DIBULATKAN | 303.450.000,00 |
Wednesday, 21 March 2018
Home »
» RENCANA ANGGARAN BIAYA RENOVASI BANGUNAN 1 LANTAI
RENCANA ANGGARAN BIAYA RENOVASI BANGUNAN 1 LANTAI
Related Posts:
PERBAIKAN KERUSAKAN PASANGAN BATU/BATA KERUSAKAN 101 Penurunan Mutu Atau Retak Pada Pasangan Batu/Bata KERUSAKAN 102 Perubahan Bentuk Atau Penggembungan Permukaan Pengge… Read More
MAKALAH MANAJEMEN RESIKO BENCANA GEMPA BUMI MANAJEMEN RESIKO BENCANA GEMPA BUMI BAB I PENDAHULUAN A. Latar Belakang Propinsi Daerah Istimewa Yogyakarta secara geograf… Read More
KERUSAKAN BETON DAN PENYEBABNYA PENGERTIAN ¡Beton adalah campuran yang terdiri atas semen, agregat halus (pasir), agregat kas… Read More
Perencanaan (Pemodelan) Transportasi Perencanaan (Pemodelan) Transportasi Apa itu … Perencanaan Transportasi ? Kenapa “transportasi” harus direncanakan ? 1. Adanya peningka… Read More
Konstruksi Interblok BAB I PENDAHULUAN A. Latar Belakang Konstruksi perkerasan lentur terdi… Read More
0 comments:
Post a Comment